Kenmare Resources plc
(“Kenmare” or the “Company” or “the Group”)
21 January 2026
Q4 2025 Production Report and 2026 Guidance
Kenmare Resources plc (LSE:KMR, ISE:KMR), one of the leading global producers of titanium minerals and zircon, which operates the
Statement from
“We achieved our revised 2025 production guidance for ilmenite and rutile and achieved and exceeded our original guidance for primary zircon and concentrates respectively. Commissioning of Wet Concentrator Plant (“WCP”) A has continued to advance during the past month, following the challenges reported in Q4, and we continue to target nameplate capacity operations at WCP A on a consistent basis in Q1 2026. Capital expenditure will be significantly reduced in the year ahead, with approximately
In light of current industry outlook, our primary operating focus for 2026 will be on value over volume, representing a shift from the historical focus on maximising production. Under this approach, we will be producing sufficient volumes to achieve product shipments of at least 1.1 million tonnes, an increase of over 15% year-on-year, which will unlock the value of the working capital contained in our current product inventories. Annual production guidance for 2026 is therefore lower than in recent years and we will also seek to limit operating costs, where possible.
Demand for Kenmare’s products remained stable in 2025 and we have a strong order book for Q1 2026. However, continued uncertainty regarding market conditions in the medium term has led us to further reduce our pricing assumptions. Consequently, we expect to recognise an impairment charge on our assets in 2025 that is not anticipated to exceed
Overview
- Lost Time Injury Frequency Rate (“LTIFR”) of 0.07 per 200,000 hours worked to 31 December 2025 (31 December 2024: 0.06), with two Lost Time Injuries (“LTIs”) in Q4 2025
- Heavy Mineral Concentrate (“HMC”) production of 1,233,300 tonnes in 2025, down 15% year-on-year (“YoY”), due primarily to lower excavated ore volumes relating to the upgrade work to Kenmare’s largest mining plant, WCP A
- Ilmenite production of 842,300 tonnes in 2025, down 17% YoY, due to lower volumes of HMC processed
- Shipments of finished products of 947,900 tonnes in 2025, down 13% YoY – two shipments were partially loaded at year-end, meaning they will be reflected in H1 2026 shipping volumes
- Net debt of
$158.8 million at 31 December 2025 (2024:$25.0 million ), with the increase due primarily to peak capital expenditure spent on the WCP A upgrade project during the year of approximately$156 million - The Company expects to recognise an impairment charge on its assets in 2025 that is not anticipated to exceed
$300 million , inclusive of the impairment charge declared in H1 2025 - Significantly reduced capital expenditure expected to be incurred in 2026, with approximately
$30 million planned to be incurred on the WCP A upgrade project and$30 million of sustaining capital– discretionary capital items are being deferred during this period of higher net debt and weaker product markets - Demand for Kenmare’s products was stable in 2025, although prices declined throughout the year due to market oversupply – Kenmare has a strong order book for Q1 2026 but this is likely to reflect weaker market pricing than experienced in 2025
- Total shipments are expected to be in excess of 1.1 million tonnes in 2026 – Kenmare intends to undertake a significant draw down of its finished product stockpiles by adjusting production
- In line with this approach, Kenmare expects ilmenite production in 2026 to be in excess of 800,000 tonnes
- Lower total cash operating costs are expected in 2026, compared to 2025, in the range of
$215 million to$225 million (at the minimum production guidance level) due to lower production volumes, the reduced use of dry mining and the implementation of other cost saving opportunities - Ongoing engagement with the Government of Mozambique regarding the extension of Moma’s Implementation Agreement (“IA”), including a second Presidential meeting in November 2025
Operations update
Operational results for the
| Q4 2025 | vs Q4 2024 | vs Q3 2025 | 2025 | vs 2024 | |
| Tonnes/%THM1 | % change | % change | Tonnes/%THM | % change | |
| Excavated ore2 | 9,215,000 | -11% | 3% | 36,958,000 | -10% |
| Grade2 | 3.36% | -32% | -17% | 4.04% | -3% |
| Production | |||||
| HMC produced | 264,300 | -39% | -11% | 1,233,300 | -15% |
| HMC processed | 267,700 | -39% | -5% | 1,215,300 | -16% |
| Ilmenite | 183,400 | -40% | -12% | 842,300 | -17% |
| Primary zircon | 10,600 | -28% | -14% | 50,000 | -1% |
| Rutile | 1,900 | -34% | 6% | 8,600 | -12% |
| Concentrates3 | 62,400 | 457% | 193% | 103,100 | 124% |
| Shipments | 231,600 | -25% | 2% | 947,900 | -13% |
- Total Heavy Mineral
- Excavated ore and grade prior to any floor losses
- Concentrates include secondary zircon, mineral sands concentrate and a new concentrates by-product, ZrTi
Kenmare’s rolling 12-month LTIFR to 31 December 2025 was 0.07 per 200,000 hours worked (31 December 2024: 0.06). While two relatively minor LTIs were incurred in Q4 2025, Kenmare achieved its lowest ever All Injury Frequency Rate of 0.75 (2024: 0.93) to 31 December, supported by its Trabalho Seguro (Safe Work) initiative.
HMC production in Q4 2025 was 264,300 tonnes, down 39% YoY. This was due to a 32% decrease in ore grades following the elimination of dry mining at WCP A, which previously targeted high-grade areas, as a cost management initiative, and a lower than expected contribution from dry mining at WCP B. Excavated ore volumes were also down 11%, largely due to the slower than anticipated production ramp up of WCP A following the upgrade work.
HMC production in 2025 was 1,233,300 tonnes, down 15% YoY, due primarily to lower excavated ore volumes relating to the WCP A upgrade work. Ore grades were down 3% YoY, with higher grades mined at WCP B in Pilivili partially offset by WCP A approaching the end of its mine path in Namalope. Encouragingly, the Selective Mining Operation (SMO) met its expected production rate of 50,000 tonnes in 2025, benefitting from a strong Q4 performance.
Production of finished products was significantly lower in Q4 2025 than in Q4 2024, largely due to lower HMC processed as a result of reduced HMC availability. Ilmenite production was 183,400 tonnes, down 40% YoY, broadly in line with the reduction in HMC processed. Primary zircon production was 10,600 tonnes, down 28% YoY, and rutile production was 1,900 tonnes, down 34% YoY, also largely due to the reduced HMC processed, but offset by significantly improved recoveries and drawdown of some intermediate stocks for processing. Concentrates production in Q4 2025 was 62,400 tonnes, up 457% YoY, due to the reprocessing of historical stockpiles delivering Kenmare’s new concentrates product, ZrTi. Kenmare expects to be able to continue to reprocess these stockpiles for the next two years, significantly supplementing ongoing ZrTi production during this time. Following successful trial shipments of ZrTi in 2025, Kenmare now sees it as a valuable by-product. Consequently, ZrTi will be included in the Company’s routine production disclosure, instead of only being recognised as production when it is shipped, as was the case during its market trial period.
Kenmare achieved revised 2025 production guidance for ilmenite and rutile and original production guidance for primary zircon. The Company materially exceeded original production guidance for concentrates.
Total production of finished products was 1,004,000 tonnes, down 10% YoY (2024: 1,115,300 tonnes), impacted by a 16% decrease in HMC processed. Ilmenite production was 842,300 tonnes in 2025, down 17% YoY, broadly in line with the reduction in HMC processed. Primary zircon production was 50,000 tonnes, down only 1% YoY, with the lower HMC processed largely offset by the decision to reprocess intermediate stockpiles and attain higher recoveries. Rutile production was 8,600 tonnes, down 12% YoY, with the lower HMC processed also partially offset by reprocessing of intermediate stockpiles. Concentrates production was 103,100 tonnes (including 59,960 tonnes of ZrTi in 2025), up 124% YoY, benefitting from the incorporation of ZrTi in production metrics.
Shipments in Q4 2025 were 231,600 tonnes, down 25% YoY, due primarily to slower loading rates on initial ZrTi shipments. Shipment volumes in Q4 2025 comprised 158,600 tonnes of ilmenite, 28,500 tonnes of primary zircon, 6,900 tonnes of rutile and 37,600 tonnes of concentrates.
Total shipments in 2025 were 947,900 tonnes, down 13% YoY, due primarily to poor weather conditions in H1 and the Peg transshipment vessel going into its five-yearly dry dock for maintenance work between June and September. Although shipment volumes in H1 were slightly stronger than in H2, the product mix was higher value in the second half of the year, as expected, with 35,500 tonnes of primary zircon shipped in H2 (H1: 14,700 tonnes) and 10,600 tonnes of rutile (H1: Nil). Kenmare also shipped 23,900 tonnes of ZrTi in 2025, which is included in concentrates production, and has identified significant ongoing demand for this product. Shipments during the year comprised 820,600 tonnes of ilmenite, 50,200 tonnes of primary zircon, 10,600 tonnes of rutile, and 66,600 tonnes of concentrates.
Closing stock of HMC at the end of 2025 was 29,200 tonnes, compared with 14,100 tonnes at the start of the year. Closing stock of finished products at the end of 2025 was 344,000 tonnes, compared with 287,200 tonnes at the end of 2024. This includes approximately 30,000 tonnes of ilmenite partially loaded at year-end. Kenmare had higher than usual levels of finished product stock at year-end and shipments are expected to materially exceed production in 2026, driving a significant reduction in finished product inventories.
Post period-end, several southern provinces of
Capital projects update
Kenmare has completed all major construction and installation work associated with the upgrade of its largest mining plant, WCP A, ahead of its transition to the Nataka ore zone. The Company is now in the final stages of the commissioning and ramp up process. WCP A’s transition to Nataka is essential to securing Kenmare’s production for decades to come. WCP A will mine in Nataka for the remainder of its economic life, which is expected to exceed 20 years.
The capital cost estimate for the WCP A upgrade, transition to Nataka and associated infrastructure remains unchanged at
While overall progress on the commissioning of WCP A in Q4 2025 was positive, some elements of the commissioning process have taken longer than anticipated, which impacted 2025 production. The ramp up of WCP A is continuing and remedial measures implemented in Q4 are working well. As the commissioning process has progressed, additional bottlenecks have been identified and the Company is undertaking a range of low-cost rectification measures in Q1 to achieve a sustainable nameplate capacity of 3,500 tonnes per hour. The extended ramp up of WCP A is not expected to impact 2026 ilmenite sales due to Kenmare’s relatively high product inventories.
Market update
Demand for all of Kenmare’s products remained stable in Q4 2025, although pricing continued to decline. This is due to the global titanium feedstocks and zircon markets remaining over-supplied, despite some reduction in supply during the year.
Globally, demand for titanium feedstocks softened in 2025, as weak housing markets and low consumer confidence led to a reduction in pigment production in
Chinese pigment production in 2025 remained broadly in line with 2024. Elevated sulphuric acid prices in
Increasing production of domestically-mined ilmenite in
The zircon market remained subdued in Q4 2025, although demand for all of Kenmare’s zircon products continued to exceed the Company’s ability to supply and Kenmare finished the year with near-zero inventories. Global zircon prices declined during Q4, due to increased supply and acceptance from customers of lower-quality zircon contained in concentrates. Encouragingly, however, prices in
Kenmare has a strong order book for Q1 2026 and the Company continues to see robust demand for its products, despite continued market softness. However, elevated feedstock inventories held by both western and Chinese pigment producers are expected continue to impact demand and pricing in 2026. These factors have led Kenmare and external commentators to take a more conservative view on the likely timing and scale of pricing recovery and market growth in the medium term, however adjustments to long-term assumptions are more modest.
Finance and corporate update
Financial position
Kenmare had cash and cash equivalents of $48.6 million at year-end (2024: $56.7 million). Gross bank loans, including accrued interest, were
The increase in net debt is due primarily to peak capital expenditure on the WCP A upgrade project during the year of approximately
Unfortunately, invoices totalling
Kenmare is meeting its funding obligations through operating cash flows, available current assets and its
Impairment charge and inventory valuation in 2025 Preliminary Results
Lower revenue assumptions associated with the continued uncertain pricing outlook outlined above are expected to result in a lower estimated recoverable value attributable to Kenmare’s mining and processing assets as at 31 December 2025. Accordingly, as this value is less than the carrying value of property, plant and equipment, an impairment will be recognised in Kenmare’s 2025 Preliminary Results. This impairment, which also reflects the latest amendments to the IA proposed by the Company (but not yet ratified by the Government), and includes amounts recognised at the half year (
Should circumstances permit, there is scope for this impairment to be reversed in future periods. Further details will be provided in the 2025 Preliminary Results.
The expected realisable market value of Kenmare’s ilmenite stocks is also impacted by the weaker pricing outlook, and in certain cases is now estimated to be below its cost of production. Accordingly, the carrying value of the stocks will be reduced to its net realisable value in the 2025 Preliminary Results, leading to an adjustment of approximately
Implementation Agreement
The IA governs the terms under which Kenmare conducts its mineral processing and export activities. Although the IA’s original expiry date was 21 December 2024, the Ministry of Industry and Commerce provided confirmation that Kenmare’s existing rights and benefits remain in full force and effect pending conclusion of the extension process. Mining operations at Moma are conducted under a separate regulatory framework, which is not impacted in any way by the IA process.
Moma’s IA continues to be a key focus and Kenmare’s Managing Director, Tom Hickey, met with the President of
Kenmare continues to engage with the Government, while reserving the right to safeguard its contractual entitlements, up to and including arbitration, if an agreement cannot be reached.
Appointment of
Kenmare appointed
2026 guidance
2026 guidance for production and operating costs is as follows:
| Unit | 2026 Guidance | 2025 Actual | |
| Shipments | tonnes | In excess of 1,100,000 | 947,900 |
| Production | |||
| Ilmenite | tonnes | In excess of 800,000 | 842,300 |
| Primary zircon | tonnes | In excess of 41,000 | 50,000 |
| Rutile | tonnes | In excess of 7,500 | 8,600 |
| Concentrates1 | tonnes | In excess of 81,000 | 106,200 |
| Costs | |||
| Total cash operating costs | $m | 215-2252 | N/R3 |
| Cash costs per tonne of finished product | $/t | 240-2502 | N/R3 |
- Concentrates include secondary zircon, mineral sands concentrate and ZrTi
- Based on minimum 2026 production guidance
- To be reported in full year financial statements
Kenmare’s focus in 2026 will be to deliver shipment volumes in excess of 1,100,000 tonnes, which represents more than a 15% uplift compared to 2025. Shipments are planned to include a significant draw down of finished product inventories.
The Company intends to produce lower volumes of finished products in 2026 than it has in recent years to minimise operating costs and accelerate the drawdown of finished product stocks. Consequently, ilmenite production is expected to be a minimum of 800,000 tonnes, with corresponding reductions in the production of primary zircon and rutile. Production will be flexed upwards from this minimum guidance level to meet market demand once inventory levels have normalised. The reprocessing of tailings to produce ZrTi is expected to supplement concentrates production and as such, concentrates production is expected to be in excess of 81,000 tonnes in 2026.
Constraining production in 2026 will allow the Company to target a reduction in operating costs compared to 2025, in line with its value over volume approach. Kenmare’s guidance for total cash operating costs in 2025 was
Expenditure on the WCP A upgrade project is expected to be
Private investor webinar via Investor Meet Company
Kenmare will host a webinar for private investors via Investor Meet Company at 2:00pm UK time today (21 January 2026).
Questions can be submitted via the Investor Meet Company dashboard at any time during the live presentation.
Investors can sign up to Investor Meet Company for free and register for the Kenmare webinar at:
https://www.investormeetcompany.com/kenmare-resources-plc/register-investor
Investors who already follow Kenmare on the Investor Meet Company platform will automatically be invited.
Notice of 2025 Preliminary Results
Kenmare plans to release its 2025 Preliminary Results on 25 March 2026.
For further information, please contact:
Kenmare Resources plc
Investor Relations
ir@kenmareresources.com
Tel: +353 1 671 0411
Mob: +353 87 663 0875
Murray (PR advisor)
Paul O’Kane
pokane@murraygroup.ie
Tel: +353 1 498 0300
Mob: +353 86 609 0221
About Kenmare Resources
Kenmare Resources plc is one of the world’s largest producers of titanium minerals. Listed on the London Stock Exchange and the Euronext Dublin, Kenmare operates the
All monetary amounts refer to
Forward Looking Statements
This announcement contains some forward-looking statements that represent Kenmare’s expectations for its business, based on current expectations about future events, which by their nature involve risks and uncertainties. Kenmare believes that its expectations and assumptions with respect to these forward-looking statements are reasonable. However, because they involve risk and uncertainty, which are in some cases beyond Kenmare’s control, actual results or performance may differ materially from those expressed or implied by such forward-looking information.
The financial information provided in this announcement is unaudited.
